General fitout info & trends · 19 Oct 2026 · by Andy Tse

Café & Restaurant Fitout Cost Sydney (2026) | Liteco Projects

Quick answer — what the build costs

120 m² café or restaurant Construction cost What it covers
Fitout $420,000
($3,500 / m²)
Demolition, partitions, ceilings, floors, joinery, bar, toilets, shopfront, finishes
+ kitchen equipment & statutory services $638,000 Cooking line, refrigeration, dishwashing, exhaust riser, grease trap, electrical upgrade, fire services

A 120 m² fitout is about 8 weeks on site. Approvals are normally a CDC through a private certifier — allow 2 to 4 weeks once the drawings are complete.

Our scope is construction: the build, the statutory services and the approvals. Commercial, leasing and accounting matters sit outside our scope.

Fitout cost per square metre

These rates are 2026 Sydney planning figures. They include our contract works and fixtures supplied and installed. They exclude loose furniture, and exclude kitchen or hospitality equipment.

Sector Rate per m² Notes
Retail — local brand, standard $2,000 – $4,500 Shopfitting, no commercial kitchen
Retail — international / luxury $4,000 – $8,000 Centre design manual, premium finishes
Hospitality — standard $2,500 – $5,000 With commercial kitchen
Hospitality — premium $4,500 – $8,000 High-end venue
Office $1,000 – $3,000 Depends heavily on existing ceiling, services and floor

Size adjusts the rate in both directions

Tenancy area Adjustment Why
Under 50 m² × 2.0 Same crew minimum charge, half a day’s work
50 – 80 m² × 1.5 Still below the efficient crew day
80 – 250 m² Baseline × 1.0 —
250 m² and above about −10% Better crew and trade efficiency
500 m² and above about −20% Volume efficiency

What is added on top of the fitout rate

Item When it applies Budget
Commercial kitchen equipment Any hot food venue $110,000 – $150,000
Grease trap / trade waste Building has none and the use requires it $30,000 – $40,000
Kitchen exhaust — straightforward Single level, direct run above roof from $15,000
Kitchen exhaust — full system Riser, fans, VSD, roof termination about $45,000
Horizontal discharge High-rise where a roof run is not achievable — needs mechanical engineer and approval electrostatic filter $25,000 – $40,000, plus the exhaust system
Shopfront replacement Not compliant, or part of the design Quoted per site
Accessible facilities No compliant access, toilets or ramp Quoted per site

Five checks that decide whether a site can trade as food

# Check What it changes
1 Can exhaust be achieved? Direct roof run where the building allows it; otherwise horizontal discharge with an electrostatic filter, subject to a mechanical engineer and approval
2 Grease trap / trade waste Required where the use produces fats and oils. Low-fat uses such as ice cream, drinks, bubble tea and bars are often exempt under trade waste guidelines — confirm with the water authority
3 Gas and electrical capacity Gas cooking equipment requires an exhaust system. Upgrades are a real cost
4 Exhaust volume and return air Make-up air must support the kitchen equipment
5 Toilets and accessibility Existing facilities may not comply or may be insufficient for the occupancy

Programme

Stage Typical duration
Design and documentation about 4 weeks
Approval — CDC via private certifier (usual path) 2 – 4 weeks
Approval — DA, only where heritage or change of use requires it Longer, and set by the consent authority. Confirm with your certifier before you sign a lease
Construction — 120 m² café or restaurant about 8 weeks
Certifier inspection and occupation certificate about 1 week

Frequently asked questions

Why does a small tenancy cost more per square metre?

Every trade carries a minimum charge for a day on site. A 40 m² shop takes the same mobilisation as a 140 m² shop, so the rate per square metre rises sharply below about 80 m².

Is the fitout rate the only construction cost?

No. Kitchen equipment, grease trap, exhaust, shopfront and accessible facilities are additional and are priced per site. We set them out separately so you can see what is base build and what is site-specific.

Do I need a DA or a CDC?

Most fitouts proceed by CDC through a private certifier, which is the faster route. A DA is required where the site is heritage listed, where there is a change of use, or where the proposal falls outside the CDC standards. Heritage can be hidden — a modern-looking shopfront can sit inside a heritage site.

Do you build to a shopping centre design manual?

Yes. Centre manuals set shopfront profile, signage illumination, ceiling and floor finishes, delivery hours and insurance levels. We read the manual before pricing.

Can you price from my drawings?

Yes. Send whatever you have — a sketch, a lease plan or an architect’s set. We will tell you what is needed to reach a fixed price.