Commercial kitchen site inspection checklist for Sydney food tenancies

Print this. Take it to the inspection. Every line you cannot tick is a line item in your budget or a reason not to sign.

A. The kitchen shell

Item What to confirm Cost if missing
Clear ceiling height above the hood Minimum workable height for a hood plus duct Rerouted or reduced services
Structural beams above the kitchen Can ductwork pass them? Rerouting, boxing, loss of ceiling height
Floor level and falls Falls to floor waste? Level changes? Screed and new drainage
Existing floor wastes Located where you need them? Core drilling and new drainage runs
Wall construction Load bearing? Can you hang equipment? Structural support and blocking
Slab / soffit condition Evidence of water damage or previous leaks Repair before fitout
Rear access Lane, roller door, loading ability Restricted supply chain and waste handling

B. Statutory services

Item Confirm Typical cost if absent
Grease trap Ground lid present; last pump-out invoice sighted $30,000 – $40,000
Exhaust hood and riser Full route traced to discharge point From $15,000; commonly $35,000–$85,000
Discharge method Roof, wall, or horizontal with electrostatic filtration Horizontal + ESP: $25,000–$40,000 per unit
Gas meter and supply size Commercial tariff? Adequate to the kitchen load? Electric kitchen or supply upgrade
Electrical main switchboard Rating, spare capacity, condition Supply upgrade
Water and hot water Capacity for a commercial kitchen Upgrade
Fire protection Sprinklers, detection, extinguishers, hose reel, exit signage Sprinkler relocation and upgrades
Mechanical ventilation Make-up air and general exhaust for the kitchen New mechanical system
Trade waste consent Sydney Water trade waste agreement in place Application, pre-treatment, delay

C. Amenities and access

Item Confirm
Customer toilets Present and compliant?
Accessible WC Present, or space to build one?
Staff amenities Change space, storage, staff toilet
Accessible entry Ramp, door width, threshold, no step
Egress paths Two exits where required, clear and compliant
Shopfront Compliant glazing, safety glass, signage zones

D. Consents and paperwork

  • What is the site currently approved for, in writing, from council?
  • Are there existing development consents you can rely on, and are they still live?
  • Is the building a heritage item or in a heritage conservation area? More here.
  • Is there a liquor licence, and does it transfer? What conditions attach?
  • Are there late-trading or noise conditions on the site?
  • Are there strata or centre by-laws on hours of works and delivery?
  • Is there an outstanding order or defect against the premises?

E. Commercial

  • Foot traffic counted at the hours you intend to trade — morning, lunch, evening, weekend.
  • Who are the five nearest competitors, and are they busy?
  • Rent per square metre versus comparable tenancies in the street.
  • Outgoings — what is included, what is recovered.
  • Bond and bank guarantee — how many months?
  • Rent-free period — and does it align to the build, not to signing?
  • Make-good obligations — what must be removed, and at whose cost?
  • Any demolition or redevelopment plan for the building.

Rule of thumb: if three or more statutory services in section B are missing or inadequate, the site is a construction project, not a fitout. Price it that way or walk away.

Send us an address and we will run this checklist against it and give you a number. Contact Liteco Projects.