Commercial Fitout Costs & Programme Sydney.

Commercial Fitout Costs & Programme Sydney

What a fitout costs and how long it takes are the two questions every client asks first. This page gives realistic 2026 planning bands for Sydney, the area adjustments that move those numbers, and the site conditions that change a project’s price by tens of thousands before a single wall goes up. The figures are planning bands, not quotes — an actual price depends on the standard of finish, the amount of joinery, the state of the base building and the services work required.

Quick reference: indicative cost per m²

Project type Indicative rate per m²
Retail / shop — local brand, standard specification $2,000 – $4,500
Retail / shop — international or luxury brand $4,000 – $8,000
Hospitality — with commercial kitchen, local standard $2,500 – $5,000
Hospitality — high-end or luxury $4,500 – $8,000
Office / workplace — basic from $1,000
Office / workplace — premium to ~$3,000

Basis: rates apply to tenancies of 80m² and above. Includes fitout works and the supply and installation of fixtures. Excludes loose furniture, loose finishes, and kitchen or hospitality equipment.

Smaller or larger spaces change the rate

Tenancy area Adjustment Why
Under 50m² ×2.0 Trades carry a daily minimum charge. A half-day job costs nearly the same as a full day.
50 – 80m² ×1.5 Same fixed costs spread over less area.
80 – 250m² baseline ×1.0 Reference band.
Above 250m² approx −10% Larger areas allow better crew and trade sequencing efficiency.
Above 500m² approx −20% Efficiency gains compound on bigger floors.

A smaller shop is not a cheaper shop. Per-square-metre, a 40m² tenancy can cost twice what a 200m² tenancy costs. The fixed cost of mobilising a team, getting approvals and running a site does not shrink with the floor area.

What pushes a hospitality project above the band

Before you sign a lease on a food site, five questions decide whether the project is even possible — and all five cost money if the answer is no.

Extra costs not included in the per-square-metre rate

Item Indicative cost
Grease trap (where required and not existing) $30,000 – $40,000
Kitchen exhaust system — typical full installation approx $45,000
Kitchen exhaust — simplest case including hood from $15,000
Electrostatic filter (required for horizontal discharge) $25,000 – $40,000 per unit
Shopfront replacement or redesign Site specific
Upgrading gas, electrical or hydraulic services Site specific

Exhaust cost rises with building height, duct length, the number of fans and whether variable speed drives are required.

Typical on-site programme

Scope On-site duration Pre-construction
Single room or small joinery package 1 – 3 weeks 2 – 4 weeks
Apartment refurbishment 6 – 10 weeks 4 – 6 weeks
Cafe or small retail tenancy 6 – 10 weeks 6 – 10 weeks
Restaurant with commercial kitchen 10 – 16 weeks 8 – 12 weeks
Office floor 8 – 14 weeks 6 – 10 weeks
Medical or dental suite 8 – 12 weeks 8 – 12 weeks
Strata common areas (staged) 4 – 10 weeks per stage 6 – 8 weeks

Pre-construction is almost always the part that gets underestimated. Design, documentation, certifier review, council assessment, strata approval and long-lead procurement all sit before the first trade walks on site, and they account for more schedule variance than construction itself.

Talk to us about your project

Send whatever you have — a sketch, a lease plan, an architect’s set, or just a description of the space. We will tell you what we need to give you a fixed price, and if the idea is not feasible in that space we will say so before you spend money on design.

Send your plans through the contact page or call (02) 8068 1755.

Figures are 2026 Sydney planning bands based on our own delivered projects. They are indicative only and are not a quotation. Actual cost depends on site conditions, documentation, scope and specification.